Project: The University of Sydney Sports & Aquatic Centre Metal Ceiling Replacement
Case Study
University of SYDney
Aquatic Centre
Location:
Cnr Codrington Street & Darlington Parade, Darlington
Size:
700 m²
Scope:
Metal Ceiling Replacement
Challenge
Metal Ceiling Replacement Challenges Above an Operational Pool
The upgrade of the Sport and Aquatic Centre at the University of Sydney presented a unique operational challenge. The existing ceiling system above the swimming pool had deteriorated due to the highly corrosive pool environment and required replacement. Works needed to be carried out directly above an active pool facility while allowing swimming programs and training sessions to continue. Maintaining pool access, protecting facility users and safely managing construction activities overhead required detailed planning and coordination.
Solution
Staged Anti-Corrosive Ceiling Installation at an Aquatic Centre
A carefully staged construction program was developed to allow the facility to remain operational throughout the project. Scaffolding was installed within the pool area and designed to maintain access to designated swimming lanes, enabling training sessions to continue each morning before works commenced later in the day. The scaffold was progressively relocated as the project advanced, allowing the removal of the corroded ceiling system and installation of a new long-life anti-corrosive ceiling solution specifically suited to the demanding aquatic environment. Close coordination with facility management ensured minimal disruption to pool operations throughout the works.
Outcome
A Durable Aquatic Centre Ceiling and MBA Award Recognition
The project successfully delivered a durable, corrosion-resistant ceiling system designed to withstand the harsh conditions of an indoor aquatic facility while significantly extending the service life of the structure. Through detailed planning, staged access arrangements and careful execution, the swimming centre remained operational throughout the project, allowing training programs and public use to continue with minimal disruption. The broader refurbishment project was recognised with the MBA Excellence in Construction Award for Refurbishment/Renovation/Extension up to $5 million, with judges specifically acknowledging the complexity of maintaining pool operations while construction works were undertaken overhead.

University of Sydney Aquatic Centre
Case Study
Location:
Cnr Codrington Street & Darlington Parade, Darlington
Size:
700 m²
Scope:
Metal Ceiling Replacement
Challenge
Metal Ceiling Replacement Challenges Above an Operational Pool
The upgrade of the Sport and Aquatic Centre at the University of Sydney presented a unique operational challenge. The existing ceiling system above the swimming pool had deteriorated due to the highly corrosive pool environment and required replacement. Works needed to be carried out directly above an active pool facility while allowing swimming programs and training sessions to continue. Maintaining pool access, protecting facility users and safely managing construction activities overhead required detailed planning and coordination.
Solution
Staged Anti-Corrosive Ceiling Installation at an Aquatic Centre
A carefully staged construction program was developed to allow the facility to remain operational throughout the project. Scaffolding was installed within the pool area and designed to maintain access to designated swimming lanes, enabling training sessions to continue each morning before works commenced later in the day. The scaffold was progressively relocated as the project advanced, allowing the removal of the corroded ceiling system and installation of a new long-life anti-corrosive ceiling solution specifically suited to the demanding aquatic environment. Close coordination with facility management ensured minimal disruption to pool operations throughout the works.
Outcome
A Durable Aquatic Centre Ceiling and MBA Award Recognition
The project successfully delivered a durable, corrosion-resistant ceiling system designed to withstand the harsh conditions of an indoor aquatic facility while significantly extending the service life of the structure. Through detailed planning, staged access arrangements and careful execution, the swimming centre remained operational throughout the project, allowing training programs and public use to continue with minimal disruption. The broader refurbishment project was recognised with the MBA Excellence in Construction Award for Refurbishment/Renovation/Extension up to $5 million, with judges specifically acknowledging the complexity of maintaining pool operations while construction works were undertaken overhead.