top of page

Get in Touch

Discuss Your Project

Request a FREE no-obligation quote and let’s talk about how we can deliver your project safely, on time and to the highest standard.

Servicing Sydney, Central Coast, Newcastle, Wollongong and East Coast NSW.

© 2026 R.O. Steel Roofing | All Rights Reserved

Asbestos roof removal and replacement at Kennards Self Storage Ultimo

Project: Kennards Self Storage Ultimo Asbestos Removal & Roof Replacement

Case Study

Kennards Self
Storage Ultimo

Location:

Ultimo

Size:

2,000 m² 

Scope:

Asbestos removal & Roof Replacement

Challenge

Asbestos Re-Roofing in a High-Traffic Inner-City Environment

Located in a busy inner-city area, this refurbishment project required asbestos removal and re-roofing in a high pedestrian and traffic environment. Road closures, crane access, traffic management and public safety all required detailed coordination.

Solution

Coordinated Crane Access & Traffic Control for a Safe Asbestos Re-Roof

R.O. Steel Roofing planned and staged the works around the restricted city site, coordinating crane operations, traffic control and safe public access. The existing asbestos roof was removed and replaced with a new Colorbond metal roofing and gutter system, together with insulation, fibreglass roof sheeting and vents.

Outcome

A Fully Renewed, Better-Performing Roof Delivered in a Complex Urban Site

The project provided Kennards Self Storage with a fully renewed roofing system while managing the complex access and safety requirements of an active urban location. The upgraded roof improved weather protection, natural light, ventilation and long-term building performance.

Asbestos roof removal and replacement at Kennards Self Storage Ultimo

Kennards
Self Storage
Ultimo

Case Study

Location:

Ultimo

Size:

2,000 m²

Scope:

Asbestos removal & Roof Replacement

Challenge

Asbestos Re-Roofing in a High-Traffic Inner-City Environment

Located in a busy inner-city area, this refurbishment project required asbestos removal and re-roofing in a high pedestrian and traffic environment. Road closures, crane access, traffic management and public safety all required detailed coordination.

Solution

Coordinated Crane Access & Traffic Control for a Safe Asbestos Re-Roof

R.O. Steel Roofing planned and staged the works around the restricted city site, coordinating crane operations, traffic control and safe public access. The existing asbestos roof was removed and replaced with a new Colorbond metal roofing and gutter system, together with insulation, fibreglass roof sheeting and vents.

Outcome

A Fully Renewed, Better-Performing Roof Delivered in a Complex Urban Site

The project provided Kennards Self Storage with a fully renewed roofing system while managing the complex access and safety requirements of an active urban location. The upgraded roof improved weather protection, natural light, ventilation and long-term building performance.